The Dolphin and Swan – Disney World
Kwik Plumbers was hired by The Dolphin and Swan Hotel in May of 2016 after a year of diligent research on the part of the Board in order to make the best repair decision for the building. The large volume of work performed was scheduled to span from May 2016 to August 2016.
The scope of work included:
- Video inspect all sanitary lines to diagnose nature of plumbing issues
- Vapor test vertical stacks
- Clean all underground and vertical drainage pipes by means of hydro jetting or mechanical sweeping
- Structurally line approximately 1410 ft of underground sanitary cast iron pipe
- Structurally line approximately 2430 ft of vertical stack sanitary cast iron pipe
- Robotically reinstate approximately 322 branch lines
- Final video inspection for presentation to board and plumbing inspector
Categories: Pipe Lining Projects / Pipe Lining
Date Posted: September 26, 2017